Bridport Street
Validation
Strip-Out
Reinstatement
Validation Strip-Out Reinstatement
We swiftly took over this long-delayed impact damage claim, rebuilding a structurally compromised wall within two months.
At Bridport Street in Portsmouth, a vehicle collision severely compromised the structural integrity of a foundation wall. To make matters worse for the policyholder, the claim stalled for over a year. Upon taking over the project, we swiftly assessed the damage and initiated the necessary work.
The affected wall was fully stripped down, including all internal fittings, before being carefully rebuilt to match the original curved design. Within just two months, we successfully completed the restoration, overcoming previous delays and ensuring the property was structurally sound and fully reinstated.